Major Project Reviews

II.1 Spaceflight Experiments Initiatives Review

Purpose

The Spaceflight Experiments Initiatives Review (SEIR) provides upper management with their first detailed look at new proposed work, and assesses the project’s reasonableness. As part of this review, the presentations for all non-advocacy reviews for spaceflight experiments are reviewed. For this review, the Head of the Space Projects Office serves as the chairperson, who selects the secretary and review panel members. The principal investigator should request that the review committee meet a minimum of four weeks prior to the response date for an Announcement of Opportunity or other request for proposals (RFP). For an unsolicited proposal, the review should be held as early as possible prior to a major commitment by the NASA Langley Research Center (LaRC).

Major Topics to be Reviewed

Software Support Needed

II.2 System Requirements Review

Purpose

The System Requirements Review (SRR) is performed during Phase B of the project’s life cycle to define its objectives and verify that the system requirements are sufficient. The major subsystems and requirements allocated to them should be clearly identified. Upon successfully completing this review, the system requirements are considered baselined.

Major Topics to be Reviewed

The system requirements.

Software Support Needed

II.3 Preliminary Design Review

Purpose

The Preliminary Design Review (PDR), held at the end of Phase B, is a formal technical review of the system design, including the various subsystems (e.g., hardware configuration items (HWCI), computer software configuration items (CSCI)) and their components. The hardware and software designs should be approximately 70% complete. All system requirements should be allocated to the various subsystems, and the subsystem and component interfaces should be well-defined. The PDR confirms that:

Major Topics to be Reviewed

Software Support Needed

II.4 Critical Design Review

Purpose

The Critical Design Review (CDR) ensures that the detailed design of each subsystem (e.g., hardware configuration items (HWCI), computer software configuration items (CSCI)) will meet the allocated system requirements, and that the project is ready to proceed with fabricating the flight system. The CDR is scheduled toward the end of Phase C when the detailed design of the hardware and software is approximately 95% complete.

Major Topics to be Reviewed

Software Support Needed

II.5 System Acceptance Review

Purpose

The System Acceptance Review (SAR) ensures that there is a high level of confidence that the flight system complies with the system requirements. The SAR also ensures that the flight system and its ground support equipment (GSE) will be safely transported to their destination, and that they will correctly operate upon arrival. The review is held after system integration and testing are completed in Phase D.

Major Topics to be Reviewed

Software Support Required

II.6 Flight Readiness Review

Purpose

The Flight Readiness Review (FRR), held at the end of Phase D, determines the overall readiness of the flight system to perform its science and mission objectives. It is held as close to the flight date as possible. The Mission Operations Review (MOR) may be held as part of this review or as a separate review.

Major Topics to be Reviewed

Software Support Required

II.7 Mission Operations Review

Purpose

The Mission Operations Review (MOR) may be held as part of the Flight Readiness Review (FRR) or as a separate subreview. The MOR determines the overall readiness of the mission operations system to support the flight system. It is held as close to the flight date as possible.

Major Topics to be Reviewed

Software Support Needed

II.8 Operational Readiness Review (ORR)

Purpose

The Operational Readiness Review (ORR), held at the beginning of Phase E, verifies that the system’s operational support elements (including the mission operations software) are ready to support system operations.

Topics to be Reviewed

Software Support Needed

II.9 Lessons Learned Review

Purpose

The Lessons Learned Review (LLR) collects and disseminates information on experiences gained during the project. These experiences should address technical, managerial, and process issues. The review panel is provided with an overview of the lessons learned. The review normally is held soon after launch and the initialization of operations.

Major Topics to be Reviewed

Software Support Needed